HARRER POOL REOPENING 2022
Harrer Pool Project
The referendum passed in March 2020, and the Park Board of Commissioners broke ground in September 2020.
November 2021-the exterior of the Harrer Pool facility is complete, the interior to be completed soon. Click here to view the final construction update.
We look forward to opening the doors and sharing the facility with the public in Summer 2022.
Questions? Contact Jeffrey Wait CPRP, Executive Director at 847-965-0383 or email at jwait@mgparks.com, or email the Park Board at board@mgparks.com.
We thank you for your continued support!
DATE | PROJECT TASK | STATUS |
---|---|---|
March 18, 2020 March 19 - April 2020 April 15, 2020 | Board Approval to proceed with Williams Architects Contract Negotiations Board Approval | Complete Complete Complete |
SCHEMATIC DESIGN (SD) | ||
April 24 - May 14, 2020 May 20, 2020 May 27 - June 2020 | Weekly SD progress meetings Board Approval SD Cost Estimate | Complete Complete Complete |
DESIGN DEVELOPMENT (DD) PHASE | ||
May 20 - June 05, 2020 June 25, 2020 July 9, 2020 July 9, 2020 July 16, 2020 July 15, 2020 | Finalize documents necessary for special use 50% DD due 50% Cost Estimate 90% DD due 100% DD due Board Approval | Complete Complete Complete Complete Complete Complete |
VILLAGE OF MORTON GROVE SPECIAL USE | ||
June 08, 2020 July 02, 2020 July 13, 2020 July 20, 2020 August 10, 2020 August 24, 2020 | Application Filed Traffic Safety Commission Meeting/Legal Notice Published Appearance Commission Meeting Plan Commission Hearing Village Trustee First Read Village Trustee Read (if necessary) | Complete Complete Complete Complete Complete Waived |
CONSTRUCTION DOCUMENTS (CDocs) PHASE | ||
August 06, 2020 August 11, 2020 August 18, 2020 August 18, 2020 September 10, 2020 September 21, 2020 | Phase I 100% CDocs - Bid/Permit Release Phase II 50% CDocs due Phase II 50% CDocs Cost Estimate Phase II 75% CDocs due Phase II 90% CDocs due Phase II 100% CDocs due | Complete Complete Complete Complete Complete Complete |
PERMIT PHASE | ||
August 06, 2020 August 25, 2020 September 24, 2020 Mid October 2020 August 24 - Mid October 2020 | Phase I Building Permit Review Permit received-Village comment received Phase II Building Permit Review Permit received IDPH Permit Review submitted IDPH Permit received | Complete Complete Complete |
BIDDING PHASE | ||
August 31, 2020 September 08, 2020 September 17, 2020 September 24, 2020 October 23 2020 October 31 2020 | First Bid Phase Pe-Bid Meeting Bids Due Special Meeting to review bid(s) Second Bid Phase Award | Complete Complete Complete Complete Complete Complete |
September 2020 - November 2021 | CONSTRUCTION PHASE | > |
November 2021 Summer 2022 | Substantial Completion Open Pool to Public |
Update: Harrer Park Gazebo
Brick Pavers at the south end of the Gazebo have been carefully removed, shrink-wrapped, and stored offsite to be installed later at Harrer Park Gazebo upon completion of the Harrer Pool project.
Updates will be posted as they become available.
May 23, 2020 Chicago Tribune – Morton Grove Champion Click to view
May 21, 2020 Harrer Pool Schematic Design – presented at the May 20th Board Meeting. Click here to view
March 23, 2020 Chicago Tribune – Morton Grove Champion Click to view
March 2020 HARRER POOL REFERENDUM PASSES
Thank you, voters! Click here to view results.
The referendum’s success enables the Morton Grove Park District to move forward with the Harrer Pool project. The Park District would like first to express its gratitude to the voters for supporting the Harrer Pool referendum. We would also like to extend a special thank you to each of those committed community members who took an active role in supporting the referendum, and to the many residents who attended our open houses to learn more. The vote demonstrates our residents’ continuing commitment to meet the recreational needs of our community and to maintain Morton Grove’s quality of life for generations to come. Your voices have been heard, and we are honored to deliver what matters most to you. As responsible stewards of your tax dollars, the Harrer Pool project will begin immediately. The first step is to create finalized drawings. If all goes according to plan, the Park District anticipates breaking ground on the replacement pool in early fall of 2020, and to open to the public in summer 2021. Please look for updates at mortongroveparks.com and on Facebook, Twitter, and Instagram. We are grateful for your continued support!